Launch Nov 27CM close Nov 30 · 11:59p MTFoundation → Nov 1Window Oct 26 – Jan 4Sources 3 Adam emails + Plan #169 + #65
Framing locked with Adam: he runs his own white-label MD Hub server, pays his own API bills, and all purchases/monthly accounts bill through his Stripe (OU merchant of record). Punch list merges his business-model brief, BFCM/Holiday plan, and Plan #65 product gaps. Demo-led path is the escape hatch if the rate card is not signed before dollar ads.
Completion by owner
Stacked status for Adam (commercial / founder) and Clark (product / engineering).
Open work by phase · Dependency readiness
Foundation ends Nov 1. Waiting-on-dependency tasks cannot start until upstream IDs are done.
Gantt — priority order with milestones
Bars run start→due. Magenta lines mark Foundation, videos, Black Friday, Cyber Monday, and holiday close.
Dates are realistic for a Nov 27 public launch under the thinner demo-led path if Foundation slips. Full self-serve BFCM + four LPs + SMS + $10k dollar ads needs the rate card this week.